36

Unpacking the Load Frame

Installation

B.

Slowly raise the load frame to its upright position. As the unit rises,
keep moving the crane to keep the chains as straight as possible.

C.

When the load frame is upright, raise it slightly to clear the shipping
pallet.

5. Move the load frame to its final location.

Before you move the load frame review the following:

The floor where the load frame will sit can bear its weight (see

“Series

311 Load Fame Weights”

on page 33).

The path to the load frame’s destination is clear and uncluttered.

The area where the load frame will sit is clean and well lit, with all
hoses and cables moved out of harm’s way.

The eyebolts are tight.

The crosshead shipping collars are properly torqued.

Lift the load frame only as high as necessary. Move it slowly to its
installation site.