DIGITAL BREW TIMER (Late Models)

FIG. 26-1 DIGITAL BREW TIMER

SERVICE (cont.)

Location:

The timer is located inside the front of the trunk

on the upper right side of component bracket.

Test Procedure

NOTE: Do not remove or install wires while timer board

is installed. Pressure applied to one side may cause

damage to the board.

1. Disconnect the brewer from the power source and

remove the front access panel.

2. With a voltmeter, check the supply voltage across

terminals TL1 and TL2 when the "ON/OFF" switch

is in the "ON" position. Connect the brewer to the

power source. The indication must be:

a) 120 volts ac for two wire 120 volt models and

three wire 120/240 volt models.

b) 200 to 240 volts ac on two wire 200 volt or

240 volt models.

3. Disconnect the brewer from the power source.

If voltage is present as described, proceed to #4.

If voltage is not present as described, refer to the Wir-

ing Diagrams and check the wiring harness.

4. With a voltmeter, check the output voltage across

terminals TL2 and TL4 when the "ON/OFF" switch

is in the "ON" position. Connect the brewer to the

power source and press the "START" switch. The

indication must be as follows:

a) 120 volts ac for two wire 120 volt models and

three wire 120/240 volt models.

b) 200 to 240 volts ac for two wire 200 volt or 240

volt models.

If voltage is present as described, the timer is operat-

ing properly. Reset the timer as required, to obtain the

desired brew volume.

If voltage is not present as described, proceed to

#6.

6. With a voltmeter, check the input start voltage

across terminals TL2 and TL5 when the "ON/OFF"

switch is in the "ON" position. Connect the brewer

to the power source and press the "START" switch.

The indication must be as follows:

a) 120 volts ac for two wire 120 volt models and

three wire 120/240 volt models.

b) 200 to 240 volts ac on two wire 200 volt or

240 volt models.

If voltage is not present as described, refer to the

Wiring Diagrams and check the wiring harness to the

start switch.

If voltage is present as described, disconnect the brewer

from the power source and replace the timer.

Removal and Replacement:

1. Remove the two #8-32 screws securing circuit

board to the mounting bracket.

2. Remove circuit board and spacers (as required).

3. Remove all wires from the timer.

4. Attach all wires to the replacement timer board

prior to installation to the component mounting

bracket. Refer to FIG. 21 when reconnecting the

wires.

5. Install new circuit board with spacers (as required)

to the component mounting bracket.

6. Adjust the timer as described in the next sec-

tion.

41711.1 052009