Dual Probe Holder 7

Publication GMSI10-UM028A-EN-E - November 2007

Installation

Follow the steps below to install the Dual Probe Holder. Refer to Figures on pages 3 and 4
for assistance. Make sure the machine is stopped before installing the Dual Probe Holder.

Prepare Mounting Surface

1. Spot face the surface, then drill and tap a hole in the machine case where you want to

install the Dual Probe Holder.

Check Parts and (if necessary) Replace Housing and Stinger O-rings

2. Open the Dual Probe Housing cover and remove plastic bag containing adjusting

cage, adjusting knob, jam nut and o-rings.

3. Replace the installed housing and stinger Viton O-rings with Buna O-rings (supplied

in plastic bag) to meet low temperature operating conditions (see table below). If you
do not need to replace the o-rings, proceed to step 4. Figure 3 on page 8 shows the
placement of the o-rings.

The table below shows the required o-rings for the appropriate temperature operating
ranges.

TIP

Follow API 670 requirements for surface finish and flatness, even for
non-API installations. If the surface is not properly prepared, it can reduce
the detection of higher frequencies.

Table 2 O-Ring Requirements

Temperature Operating Range

Required O-ring

-10 to 400°F (-23 to 204°C)

Viton O-ring (default)

-30 to 230°F (-34 to 110°C)

Buna O-ring