THERMAL ARC 161 S

Manual 0-5199

4-7

Operation

4.13 Joint Preparations

In many cases, it will be possible to weld steel sections without any special preparation. For heavier sections and for

repair work on castings, etc., it will be necessary to cut or grind an angle between the pieces being joined to ensure

proper penetration of the weld metal and to produce sound joints.
In general, surfaces being welded should be clean and free of rust, scale, dirt, grease, etc. Slag should be removed

from oxy-cut surfaces. Typical joint designs are shown in Figure 4-110.

Gap varies from

1/16" (1.6mm) to 3/16" (4.8mm)

depending on plate thickness

Joint

Open Square Butt

1/16" (1.6mm) max

1.6mm (1/16”)

Single Vee Butt Joint

Not less than

70°

Double Vee Butt Joint

1/16" (1.6mm)

Lap Joint

Tee Joints

(Fillet both sides of the

joint)

Edge Joint

Fillet Joint

Corner Weld

Plug Weld

Plug Weld

Not less than

70°

Single Vee Butt Joint

Not less than

45°

1/16" (1.6mm) max

Art # A-10367

Figure 4-11: Typical joint designs for arc welding