3.1 Unpacking

Pull out the nails with which the shell is fastened to the transport pallet. The
shell is the wooden box that is situated over the transport pallet.

Lift the shell off the transport pallet.

Compare the contents of the delivery with your order.

3.2 Transport

Transport with a forklift or elevating truck while on the trans-
port pallet.

Use the ring bolt H for transport of the cross beater mill.

Do not stand under the transport pallet!

3.3 Setup

Lift the cross beater mill off the transport pallet.

Observe the accident prevention guidelines VBG 8, VBG 9a and VBG 9!

Set up the cross beater mill horizontally on a level and stable indoor
surface. It is not necessary to fasten the device in place.

Operation of the cross beater mill while it is on the transport pallet is
not permitted!

Ensure easy access to the cross beater mill.

The ambient temperature must range from 5–40 °C.

The max. humidity up to 31 °C is 80 % and declines linearly to 50 % at
40 °C.

The minimum elevation for setup and use of the device is 200 m below
sea level.

3.4 Setup on a laboratory table

You can also mount the cross beater mill onto your labo-
ratory table.

Measure the laboratory table thickness.

Use screws with a max. diameter of 8 mm and a
length of the laboratory table thickness plus 25 mm.

Place the cross beater mill including collecting ves-
sel on the table.

Mark the hole locations onto the table using the ex-
isting holes on the motor of the cross beater mill.

The spacing from the holes to the front edge of the table must allow sufficient
space for installation and removal of the collecting vessel and the filter hose.