AM Series Cascade Sequencer
INSTALLATION AND OPERATION MANUAL
Wiring the Manager Heater communications Board – Continued
6. From the wire conduit, remove the two wires (pink and yellow) that are attached to the plug
disconnected from the communications board in step 4.
Figure 1-8: Removing Pink and Yellow Wires from Wire Conduit
7. Cut the connector from the pink and yellow wires and strip the insulation 1/4” (7mm).
Figure 1-9: Removing 2-Wire Connector from Junction PCB
8. Connect the pink wire together with the two black wires present on terminal #16 (See
Figures 1-10 and 1-12).
Figure 1-10: Connecting Pink Wire to Terminal #16
Wire
Conduit
Yellow & Pink
wires cut from
connector
and stripped.
Page 10 of 26