1.1 Piping Installation

WARNING!

Prior to appliance installation and/or maintenance, disconnect the

appliance’s electrical power supply and shut off the inlet gas

valve. Failure to follow these instructions could result in severe

personal injury or death!

In order for the AM Cascade Sequencer to operate correctly, the AM Series heaters must be

installed as shown in Figure 1-1.
Because the cascade general sensor is installed on the Manager heater, the managing heater

must always be the closest to the low loss header in order to provide the most accurate

temperature measurement.
A maximum of eight (8) heaters may be connected into the cascade system.
At the time of the installation all heaters will have the same settings. After installation, the heater

nearest the low loss header will require some hardware adjustment to become the managing

heater, and the other heaters will need a change to the software settings to become the

dependent heaters. Instructions for doing this are provided in the following sections.

NOTE

Figure 1-1 shows only one piping configuration example. Other

piping configurations are possible. Contact AERCO technical

support for information concerning alternative configurations.

Figure 1-1: Cascade Sequencing Heater/Boiler Piping Installation