1 electrical power requirements, Benchmark 1.5ln low nox boiler, Gf-120 – AERCO BMK 1.5 LN July 2011 User Manual

Page 20

Advertising
background image

CHAPTER 2: INSTALLATION

Page

20 of 152 PR2: 05/09/12

Benchmark 1.5LN Low NOx Boiler

Operation and Maintenance Manual

OMM-0041_0D

GF-120

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913 • Ph: 800-526-0288

UPPER RIGHT CORNER OF FRONT PANEL

TERMINAL BLOCK

Figure 2-7: AC Input Terminal Block Location

Electrical Power Requirements

2.8.1

The AERCO Benchmark 1.5 Boiler accepts 120 VAC, single-phase, 60 Hz @ 20 A. The Power

Box contains a terminal block as shown in Figure 2-8. In addition, a wiring diagram showing the

required AC power connections is provided on the front cover of the Power Box.
Each Benchmark 1.5 Boiler must be connected to a dedicated electrical circuit. NO OTHER

DEVICES SHOULD BE ON THE SAME ELECTRICAL CIRCUIT AS THE BENCHMARK

BOILER.
A double-pole switch must be installed on the electrical supply line in an easily accessible

location to quickly and safely disconnect electrical service. DO NOT attach the switch to sheet

metal enclosures of the unit.
After placing the boiler in service, the ignition safety shutoff device must be tested. If an external

electrical power source is used, the installed boiler must be electrically bonded to ground in

accordance with the requirements of the authority having jurisdiction. In the absence of such

requirements, the installation shall conform to National Electrical Code (NEC), ANSI/NFPA 70

and/or the Canadian Electrical Code (CEC) Part I, CSA C22.1 Electrical Code.
For electrical power wiring diagrams, see the AERCO Benchmark 1.5 Electrical Power Wiring

Guide, (GF-4060).

GND

NEU

L1

120 VAC, 1 PHASE

Figure 2-8: AC Terminal Block Configurations

Advertising