4.4 NATURAL GAS COMBUSTION CALIBRATION

The Benchmark 1.5LN Boiler is combustion calibrated at the factory prior to shipping. However,

recalibration as part of initial start-up is necessary due to changes in the local altitude, gas BTU

content, gas supply piping and supply regulators. Factory Test Data sheets are shipped with

each unit. These sheets must be filled out and returned to AERCO for proper Warranty

Validation.
It is important to perform the following procedure as outlined. This will keep readjustments to a

minimum and provide optimum performance.

1. Open the water supply and return valves to the unit and ensure that the system pumps

are running.

2. Open the natural gas supply valve(s) to the unit.
3. Set the control panel ON/OFF switch to the OFF position.
4. Turn on external AC power to the unit. The display will show LOSS OF POWER and the

time and date.

5. Set the unit to the Manual Mode by pressing the AUTO/MAN key. A flashing Manual

Valve Position message will be displayed with the present rate in %. Also, the MANUAL

LED will light.

6. Adjust the air/fuel valve position to 0% by pressing the ▼ arrow key.
7. Ensure that the leak detection ball valve down-stream of the SSOV is open.
8. Set the ON/OFF switch to the ON position.
9. Change the valve position to 29% using the ▲ arrow key. The unit should begin its start

sequence and fire.

10. Next, verify that the gas pressure downstream of the SSOV is 3” W.C. for both FM and

IRI gas trains. If gas pressure adjustment is required, remove the brass hex nut on the

downstream SSOV actuator (IRI gas train) to access the gas pressure adjustment screw

(Figure 4-4). Make gas pressure adjustments using a flat-tip screwdriver to obtain 3”

W.C.

BRASS HEX

HEAD CAP

(REMOVE TO

ACCESS GAS

PRESSURE

ADJUSTMENT

SCREW)

SSOV ACTUATOR

Figure 4-4: Gas Pressure Adjustment Screw Location