7 Commissioning

This menu allows you to carry out the necessary operations on

the appliances following installation.

1

Select Commissioning on

the screen.

7.1

Filling the heating circuit

i

The Systempro control unit is used to open the valves

of each zone during fi lling, if more than one heating

zone is installed.

1

Select Fill htg circuit on the

screen

2

Activate Begin fi lling

procedure.

Refer to the boiler instructions for fi lling the boiler.

7.2

Venting the heating circuit

Venting of the heating circuit enables the purging of any air in the

heating circuit.

Open the diff erent heating circuit air vent.

1

Select Air venting on the

screen.

2

Select Vent heating circuit

on the screen.

b

When venting is complete, close the diff erent heating

circuit air vent.

7.3

Venting the HP circuit

This function can only be activated for an eBus heat pump. In the

case of an On/Off heat pump, perform this operation with the

parameterisation tool supplied with the heat pump.

The venting of the HP circuit allows you to purge any air in the HP

circuit.

1

Select Vent HP circuit on

the screen

2

Start the venting

procedure.

7.4

Adjustment of HP circuit fl ow

This function can only be activated for an eBus heat pump. In the

case of an On/Off heat pump, adjustment of the HP circuit fl ow is

not possible.

1

Select on the screen

Glycol circuit fl ow.

2

Start the reading of the

heat pump circuit fl ow rate.