Installation – Glow-worm Ultracom2 sxi User Manual

Page 26

Advertising
background image

0020092785_02 - 05/10 - Glow-worm

- 24 -

12 Commissioning

i

At the time of commissioning, complete all relevant

sections of the Benchmark Checklist located in the

centre pages of this document.

The commissioning should be carried out by a competent

person approved at the time by the Health and Safety Executive

and in accordance with the current issue of BS6798.

12.1 Switching on

• Do not operate the boiler without water.

• Make sure that the system has been thoroughly flushed out with

cold water and that all cleanser if used has been removed.

• With the gas service isolation valve closed, with no demand

from any external controls and the power supply to the boiler

switched off.

• Test for gas soundness and purge air from the gas supply.

• Press the on/off button to activate the appliance.

• Make sure that the domestic hot water and heating functions

on your appliance are not activated.

12.2 filling the CH system (Central heating)

• Make sure that the installation's cold-water inlet isolating

valve is open.

• Open the isolating valves located on the connections: they

must be positioned in the direction of the flow.

If the Central Heating (C.H.) pressure falls below 0.4 bar, the

display will flash the current pressure and the boiler will not

operate. To increase the pressure, the CH circuit requires

"Topping up".

i

When turning the 230Vac supply on to the boiler

should the water pressure be less than 0.5 bar an

automatic air vent function will be activated for a

period of 5 minutes. During this time the pressure

should be increased and air vented from the system.

During this time the burner will not fire in either CH

or DHW mode and the display will blink displaying

the current water pressure.

• Vent air from each radiator until the water flows normally,

then close the vents.

• Leave the pump's air vent open.

i

The following two operations will unblock the pump's

engine after a prolonged storage period and will

purge the air from the pumps circuit.

• Remove the screw from the pump shaft and introduce a flat

screwdriver. A trickle of water, under no pressure, should

normally come out of the pump.

• Rotate the pump shaft through several turns, then replace

the screw.

12.3 filling the Condensate Trap

A

B

C

1

1

2

Key

1 filling trap

2 Condensate trap

• Fill the trap 3/4 full with water (1).

• Activate the Heating and, if Glow-worm intelligent controls

are fitted, Domestic Hot Water functions.

• Run the appliance for at least 15 minutes, with a heating

temperature set to greater than or equal to 50°C (not

applicable for an installation with underfloor heating).

• Vent air from each radiator again until the water flows

normally, then close the vents.

• If you have difficulties in removing the air, launch the air-

removal programs in the heating circuit (see the chapter

("Technical settings for the appliance and list of parameters").

• Make sure that the pressure indicator shows a value of 0.8

bars; otherwise, fill the appliance again.

12.4 Initial lighting

12.4.1

Control

i

The combustion for this appliance has been

checked, adjusted and preset at the factory for

operation on natural gas (G20) as defined on the

appliance data label.

No measurement of the combustion is necessary.

Should the appliance require to be converted to LPG

gas ensure you follow the gas conversion section

before lighting the boiler.

• Check that the appliance has been installed in accordance

with the instructions.

• Check the integrity of the flue system and flue seals.

INSTALLATION

Advertising