Maintenance – Glow-worm Ultracom2 sxi User Manual

Page 40

Advertising
background image

0020092785_02 - 05/10 - Glow-worm

- 38 -

18.2 Casing removing

18.2.1

front panel

24

V

230

V

2

1

A

A

B

Key

1 front panel

2 Front panel retaining screw

• Undo the two screws (2) on the underside of the front panel

and remove the front panel (1).

18.2.2

Control box

24

V

230

V

1

Key

1 Control box

• Position the control box (1) into the service position.

18.3 Combustion check and setting the air/gas

ratio valve

18.3.1

Competency to carry out the check of

combustion performance

i

BS 6798: 2009 Specification for installation and

maintenance of gas-fired boilers of rated input not

exceeding 70kW net advises that:

- The person carrying out a combustion measurement must be

assessed as competent in the use of a flue gas analyser and

the interpretation of the results.

- The flue gas analyser used should be one meeting

the requirements of BS7927 or BS-EN50379-3 and be

calibrated in accordance with the analyser manufacturers’

requirements.

- Competence can be demonstrated by satisfactory completion

of the CPA1 ACS assessment, which covers the use of

electronic portable combustion gas analysers in accordance

with BS 7967, parts 1 to 4.

• Ensure that the gas analyser is set to the correct fuel setting.

• Select the “ ”, constant central heating function by pressing

the “

” button repeatedly, refer to commissioning

section. The boiler should fire automatically.

i

Safe combustion can only be verified by measuring

CO/CO2 ratio. This must not exceed the value

shown in the table opposite.

18.3.2

Preliminaries

Prior to, during servicing and after any maintenance or changed

parts, the following must be checked.

• The integrity of the flue system and flue seals.

• The integrity of the appliance combustion circuit and relevant

seals.

• Electrical, gas and water connections.

• System pressure.

• The combustion performance, refer to the following

procedure.

• The operational gas inlet pressure and gas rates, refer to

the commissioning section paragraph 12.5. Correct any falt

before continuing.

Combustion check and setting the air/gas ratio

• Remove the front casing panel, see diagram above and

hinge down the control box. Taking care not to touch any

internal components, proceed as follows:

• Connect the CO2 combustion analyser to the relevant test

point, see diagram opposite.

MAINTENANCE

Advertising