16 Routine Cleaning and Inspection

To ensure the continued efficient and safe operation of the
boiler it is recommended that it is checked and serviced at
regular intervals. The frequency of servicing will depend upon
the particular installation conditions and usage, but in general
once a year should be enough.

It is the law that any servicing is carried out by a competent
person.

All parts are replaced in reverse order to removal.

16.1 Products of combustion check, refer to
diagram 16.1

Note: To obtain a products of combustion reading, unscrew the
left hand sampling point cap on the flue elbow, located on top
of boiler.

Connect the analyser tube onto sampling point.

Switch on the electrical supply and gas supply, then operate
the boiler.

On completion of the test switch off the electrical supply and the
gas supply, remove analyser tube and replace sampling point
cap.

Diagram 16.2

16.6 Side panels

(For ease of access if required)

• Unscrew and remove the four screws securing lower grille
onto boiler. Unhook grille from rear of boiler and remove.

• Remove three screws from front of each side panel.

• Unclip the toggle clip at the top of each side panel.

• Lift each panel up and then forward to remove.

16.7 Combustion chamber cover

• Unscrew the two screws securing combustion chamber cover
to combustion chamber then unclip the two toggle clips, see
diagram 16.3
.

• Remove combustion chamber cover from boiler.

Diagram 16.3

16.2 Service Check and Preparation.

• Operate boiler and check for any faults that need to be put
right.

• Isolate boiler from the gas and electrical supplies.

• On completion check all gas-carrying parts for soundness with
leak detection fluid.

• Remove boiler casing as follows:

16.3 Front panel

• Unscrew and remove the two front panel retaining brackets
from the top of the boiler.

• Remove panel by lifting up and forward.

16.4 Control panel

• Lift control panel up and lower forwards to gain access to lower
part of boiler.

16.5 Sealed chamber cover

• Unclip the two toggle clips holding the sealed chamber cover,
see diagram. 16.2
.

• Lift cover up and off boiler.

9318

PRODUCTS
SAMPLING
POINT

10022

9950

Diagram 16.1