background image

Select “hotfix_pcie_2GiB-1.0.0.pkg” and any licenses that appear in the Ingest window.

Click the Ingest button.

After ingesting, reboot the unit.

Once the reboot is complete, launch the License Manager application to confirm that the
licenses have been ingested properly.

5.4 Installing the IMB to the ShowVault

Install your IMB into your Series-2 digital cinema projector. Please reference the specific IMB
Installation manuals that coincide with your projector manufacturer and the ShowVault Field
Installer manual found at

http://www.doremilabs.com/support/cinema-support/cinema-

manuals/showvault-imb-manuals/

.

5.5 Testing the Unit

After the IMB and ShowVault have been installed, and marriage performed, the unit is
now ready for playback testing. Confirm that picture and sound are present.

6 Returning the Media Block

Now that your Doremi Server has been converted to a ShowVault, you must now return the
Dolphin Media Block and the AES card that you removed during the procedure back to Doremi.

Package up the Dolphin Media Block, AES card, and1GB RAM modules (if you needed to
update to 2GB) in the antistatic bag in the original packaging provided. Write the RMA #
provided to you on the outside of the box that the conversion kit was shipped in and return to
your local Doremi Cinema to receive your media block credit.

You have now successfully completed the conversion process.