AMETEK SFA Series Ethernet Programming User Manual
Page 124

SCPI Command Operation
SG Series Programming
6-52
M550129-03 Rev K
OUTP:STAT ON
PROG:STAT RUN
Following is a diagram for Example 4.
Figure 6-4. End-of-Sequence Pause for Example 4
EXAMPLE 5
To make a sequence longer than the maximum of 20 steps in an ordinary sequence, there
are either one of two ways or a combination of the two. One way is to use the
SUBCALL
command. The second way is to use the
GOTO
command. The use of the
SUBCALL
command was shown in Examples 3 and 4 above. Now join two 20-step sequences with a
GOTO
command.
First, create a sequence wherein the power supply output will simulate a capacitor charge
curve to a maximum of 10 volts and discharge curve to zero volts.
3 volts for 10 sec
3 volts for 10 sec
5 volts for 10 sec
Ramp up to 5
volts in 10 sec
Ramp down to 3
volts in 10 sec
10 volts for 5 sec
Ramp down to
2 volts in 9 sec
4 volts for 6 sec and
then pause indefinitely