2 square pole, 3 spar installation – Comtech EF Data KST-12000 User Manual
Page 68

KST-12000 Ku-Band Satellite Terminal
Revision 4
Redundant System Installation
MN/KST12000.IOM
3.3.2.2 Square Pole
For square vertical pole installation, follow the steps in Section 3.3.2.1, with the
following exceptions:
• Do not perform Step 4.
• Do not perform Step 6.e.
3.3.3 Spar Installation
Note: The following process is for a typical installation. Custom kits may be ordered and
are beyond the scope of this manual.
To install the RFTs to a spar:
1. Set the units on their side, with the mounting holes facing up.
2. Install the 8” unistruts as follows:
a. Position an 8” unistrut (with the open
side facing up) over one set of the
mounting holes on the RFT.
b. Using four 1/4-20 bolts, 1/4” split
lockwashers, and 1/4” flat washers,
attach an 8” unistrut to the RFT.
Tighten the bolts firmly.
c. Repeat Steps 2.a. and 2.b. for the
remaining 8” unistruts (for a total of
four).
3–16