5.3 Startup

You can start up the Sunny Boy 3800 when
• The AC (mains) cable is connected correctly
• The DC cables are fully connected and the unused DC plug connectors on the

bottom of the enclosure are closed using the protective caps

• The enclosure's cover is securely screwed on
• You are sure that the input voltage cannot exceed 600 V, and
• The DC input voltage is sufficient for supplying the onboard electronics.

How to start up the inverter

1.

First of all, switch the line circuit breaker to the
"on" position.

2.

Now look at the LED display and consult the
table below to check whether the Sunny Boy
3800 is in a fault-free operating status and that
you understand what this status means. Once
the inverter is in a fault-free operating status,
startup has successfully completed.

On!

Off

Netzwechselrichter für Windenergieanlagen

Netzwechselrichter für Windenergieanlagen

Grid tied inverter for wind turbines

Grid tied inverter for wind turbines

Windy

Boy

Pac 903W

Upv 330V

Advertising
This manual is related to the following products: