Setting up a verify schedule – Avago Technologies 3ware SAS 9750-4i User Manual
Page 74
 
Chapter 2. CLI Syntax Reference
66
3ware SATA+SAS RAID Controller Card CLI Guide, Version 10.0
Setting Up a Verify Schedule
Setting up a verify schedule requires several steps, and several different CLI 
commands in addition to /cx add verify.
To set up the verify schedule you want to use, follow this 
process:
1
Use the /cx show verify command to display the current schedule for 
verify tasks. (For details, see page 53.)
2
If any of the scheduled tasks do not match your desired schedule, use
the /cx del verify command to remove them. (For details, see page 68.)
3
Use the /cx add verify command to create the verify schedule slots you 
want (described above.)
4
Use the /cx set verify=enable command or the /cx set verify=advanced 
to enable the schedule (this enables all rebuild schedule slots). (For 
details, see page 71.)
5
Use the /cx/ux set autoverify=on command to turn on autoverify for each 
unit you want to follow the schedule. (For details, see page 90.)
Note:
If you do not enable autoverify for units or start a verification manually, no
verifies will run during your verify task schedule, even if the verify schedule is 
enabled with the /cx set verify=enable command or the /cx set verify=advanced.
Warning:
If all time slots are removed from the verify task schedule, be sure to
also disable the schedule. Otherwise verify tasks will never occur.