14 adapting three-phase transfer switch, 15 control board configuration, 16 grounding the generator – Generac 04077-01 User Manual

Page 17

Advertising
background image

Generac

®

Power Systems, Inc. 15

1.14 ADAPTING THREE-PHASE

TRANSFER SWITCH

The generator you are installing may include a

prepackaged transfer switch configured for three-

phase loads. If you want to adapt this kind of transfer

switch for single-phase loads, proceed as follows:
1. Discard the three-phase power monitor (PM)

found inside the enclosure. You will not use it

with a single-phase system.

2. Locate the eight-pin octal relay socket in the lower

left corner of the transfer switch enclosure.

3. Move Wire N1A from Terminal 8 to Terminal 1 by

cutting the lug off of N1A , stripping wire 5/16"

from end, and inserting the wire under screw of

Terminal 1.

NOTE:

Moving N1A from Terminal 8 to Terminal 1 takes
the three-phase voltage monitor out of the sensing
circuit. Now, the control circuit board in the con-
trol module assembly (CMA) senses utility voltage.

4. Now, connect the control wires as follows:

• Connect Utility Supply to lugs N1 and N2.
• Connect the Customer Load lugs T1 and T2.
• Connect the Standby Supply to lugs E1 and E2.

1.15 CONTROL

BOARD

CONFIGURATION

The control board for the 6 kW, 8 kW and 10 kw has

four dip switches (see Figure 1.12), which may be set

up differently during installation.
1. Dip switch 1: When in the ON position, the board

requires 20 Vac from the step down transformer

to the control board to determine if utility is

present. This switch is factory preset and should

not need to be changed. This switch should be set

in the OFF position.

2. Dip switch 2: When in the ON position, it will

disable the automatic starting of these units.

This should be set when utility is not present at

the installation location. This is the only switch

that may need to be set to the ON position for

these models.

3. Dip switch 3: It will allow for 50 Hertz opera-

tion and is not applicable to these models. This

switch is factory preset and should not need to

be changed. This switch should be set in the

OFF position.

4. Dip switch 4: It has no function at this time.

Figure 1.12 – Control Board Configuration

1.16 GROUNDING THE GENERATOR

Generally, connecting a No. 12 AWG stranded copper

wire to the grounding lug (Figure 1.13) and to an earth-

driven copper or brass grounding rod (electrode) will

adequately ground the generator. However, local codes

may vary widely. Consult with a local electrician for

grounding requirements in your area.

Figure 1.13 – Grounding the Generator

Section 1 — Installation

Guardian Air-cooled Generators

Advertising
This manual is related to the following products: