BJ5-620 Installation 22

of

73

Chapter 3: Installation

3-1 Uncrating the Equipment

Requirements at Application Site

Check the application site to make sure it conforms to the qualifications listed below.

The site has enclosed space.

The ground has sufficient load-bearing capacity (refer to the “Technical
Specifications” in the Appendix for machine weight). The unevenness of the
ground surface may not exceed 5 mm.

The machine must be freely accessible from all sides.

There must be sufficient room for operating and service personnel.

Spatial requirements: Refer to the “Drawings and Diagrams” in the
Appendix for machine dimensions. All hinged parts must be able to be
opened completely.

The site is a vibration-free environment.

The site has sufficient lighting.

The machine may not be exposed to direct radiation caused by radiators or
the sun.

Room temperature: +41 to 104 °F (+5° to +40°C)

Relative atmospheric humidity according to DIN 40040:

15 to 70 % (indoor)

NOTE: By humidity levels higher than 70 %, apply anticorrosive agent

to the metallic-finished machine parts. Insulation for the
tropics is also necessary.

The machine may not be operated within range of static discharges or strong
magnetic fields as this could lead to faults in the machine control system.

Unloading and Installing the Machine

The machine and components are packed so they arrive safely. Use a suitable crane or
forklift for unloading the packaged machine and/or components.

1. Remove the packaging material and all transportation safety devices after

unloading the machine.

2. In the case that the shredder and its accessory components have been

delivered as individual items, mount these at the site of application in
accordance with the Assembly Drawing. This is the only way to
guarantee there are sufficient piping parts, tubing, and cable connections,
and that the linking places match.