NOTE: DIAGRAMS & ILLUSTRATIONS ARE NOT TO SCALE.

17

Framing Dimensions for Roof

Inches (millimeters)

Pitch

C

D

0/12

10-1/2 in.

(267 mm)

10-1/2 in.

(267 mm)

6/12

10-1/2 in.

(267 mm)

12 in.

(305 mm)

12/12

10-1/2 in.

(267 mm)

17 3/4 in.

(451 mm)

Figure 25

- Roof Framing

C

D

Storm

Collar

Figure 27

Flashing

Figure 26

If the vent system extends more than 5 feet (1.5

m) above the roof flashing, stabilizers may be

necessary. Additional screws may be used at

section joints for added stability. Guide wires

may be attached to the joint for additional sup-

port on multiple joint configurations.

Use a carpenter’s level to measure from a

constant surface and adjust the support straps

as necessary.

It is important to maintain the required clear-

ances to combustibles: 1" (25 mm) at all sides

for all vertical runs; and 3" (76 mm) at the top,

1" (25 mm) at sides, and 1" (25 mm) at the

bottom for all horizontal / inclined runs.

H. Frame roof opening - Identify location for

vent at the roof. Cut and/or frame opening per

Roof Framing Chart and Figure 25.

K. Install the vertical termination - The final

Step involves installation of the SV4.5CGV-1

Vertical Termination. Extend the vent sections

to the height as shown in the "Vertical vent

termination section" (Page 6, Figures 3A and

3B). The SV4.5CGV-1 Vertical Termination

(Figure 27) can be installed in the exact same

fashion as any other Secure Vent section. Align

the termination over the end of the previously

installed section, adjusting the radial alignment

until the four locking dimples of the termination

are aligned with the inlets of the four incline

channels of the last vent section. Push the ter-

mination down until it fully engages, then twist

the termination clockwise running the dimples

down and along the incline channels until they

are seated at the end of the channels.

I. Install the roof flashing - Extend the vent

sections through the roof structure. Install the

roof flashing over the vent section and position

such that the vent column rises vertically (use

carpenters level - see Figure 26 ). Nail along

perimeter to secure flashing or adjust roofing

to overlap the flashing edges at top and sides

only and trim where necessary. Seal the top

and both sides of the flashing with waterproof

caulking.

J. Install the storm collar - Install the storm

collar, supplied with the flashing, over the vent /

flashing joint. See Figure 26. Loosen the storm

collar screw. Slide collar down until it meets

the top of the flashing. Tighten the adjusting

screw. Apply non-combustible caulking or

mastic around the circumference of the joint

to provide a water tight seal.