6.2 Shelf Mounting and Suspension

Four suspension points (3/8" nuts) are located on
the top of the heater. Drop rods must be 3/8"
diameter mild steel minimum.

When handling or supporting the heater from below,
ensure that the weight is taken at the support points.
For typical suspension,

See Page 10, Figure 5.

For typical shelf mounting on existing shelf,

See

Page 11, Figure 6.

The gas or electrical supply lines must not be used
to support the heater.

Do not locate the gas or electrical supply lines
directly over the path of the flue products from the
heater.

The heater must be installed in a location that is
readily accessible for servicing.

The heater must be installed in accordance with
clearances to combustibles as indicated on the wall
tag and in this manual.

6.3 Wall Mounting

For typical suspension,

See Page 11, Figure 7. Wall

mounted heaters blowing parallel to the wall can
only be installed with the service door away from the
wall.

The wall mounting brackets must be attached to a
suitable wall using all mounting holes. Screw sizes
less than 3/8" may not be used. In order for the wall
mounting brackets to adequately carry the weight of
the heater, it must be installed according to best
building practices.

Figure 5: Suspension Methods

WARNING

Crush Hazard

Use 3/8" threaded rod
minimum.