assembly sTePs

Note: The following steps represent the normal

sequence of installation. Each installation is

unique, however, and might require a different

sequence.

1. Position firebox prior to framing or into

prepared framing.

. Install the chimney system.

3. Install outside combustion air kit.

4. Plumb gas line if a decorative gas appliance

will be used. (Gas connections should only

be performed by an experienced, licensed/

certified tradesman).

5. Install both “All-Glass

TM

” door assemblies.

6. Complete finish wall material, surround and

hearth extension to your individual taste.

7. Inststall the glass doors provided.

Study the three dimensional illustration (Figure

1) to get a general idea of each element of your

fireplace system.

Pre-InsTallaTIon noTes

The fireplace may be installed directly on a

combustible floor or raised on a platform of

an appropriate height. Do not place fireplace on

carpeting, vinyl or other soft floor coverings. It

may, however, be placed on flat wood, plywood,

particle board or other hard surfaces. Be sure

fireplace rests on a solid continuous floor or

platform with appropriate framing for support

and so that no cold air can enter the room from

under the fireplace.

The fireplace may be positioned and then the

framing built around it, or the framing may be

constructed and the fireplace positioned into

the opening.

Usually, no special floor support is needed for

the fireplace, however, to be certain:

1. Estimate the total weight of the fireplace

system including chimney and surround

materials such as brick, stone, etc., to be

installed. Shipping weights for the fireplace

may be found on Page 7.

The firestop thimble supplied with the unit must

be used on a manufactured home installation.

The firestop thimble must extend completely

though the roof cavity to the outermost plane

of the roof (See Figures 21, 22 and 23).

Maintain 1" clearance between the thimble and

the chimney.

If you plan to raise the fireplace and hearth

extension, build the platform assembly then

position fireplace and hearth extension on

top. Secure the platform to the floor to prevent

possible shifting.

clearances

Minimum clearance to combustibles for the

appliance is as follows: sides - 1/2" (12.5 mm),

floor - 0" (0 mm), adjacent wall - 18" (457 mm),

ceiling - 37-1/2" (953 mm).

Note: Install the hearth extension only as il-

lustrated.

hearth

extension

floor

hearth

extension

metal safety

strips

floor

hearth

extension

floor

hearth

extension

metal safety

strips

Platform

cauTIon

do not block the heat-circulating

air inlet and outlet ports. doing

so may result in a potential fire

hazard.

cauTIon

The structural integrity of the

manufactured home floor, wall,

ceiling and roof must be main-

tained.

InsTallInG The fIrePlace

step 1. Slide the fireplace into prepared framing

or position fireplace in its final position

and frame later.

The fireplace may not be recessed into a

combustible floor. Maintain the floor to hearth

clearance established by the fireplace lower

front face.

step . Insert the provided metal safety strips,

beneath the fireplace as illustrated

(Figures 6 and 7). The safety strips

should overlap 1/2" for continual

coverage of the floor.

Note: Safety strips are not required when fire-

place rests on a noncombustible surface.

. Measure the square footage of the floor space

to be occupied by the system, surrounds and

hearth extensions.

3. Note the floor construction, i.e. 2 x 6’s, 2 x

8’s or 2 x 10’s, single or double joists, type

and thickness of floor boards.

4. Use this information and consult your local

building code to determine if you need ad-

ditional support.