14.11

Shrink down the end of the sleeve on

the cable side. Heat till the sleeve shrinks down
onto the cable and the green
thermo-indicating paint is converted to black. A
ring of red adhesive should be visible at the
cable on the end of the sleeve.

Wait until the sleeve is cool to the touch
before moving the cables.

14.13

Re-install the sealing ring, the dome and the clamp (see section 12).

15

Additional cable installation

15.1 For each added cable use a FOSC-B/D-CSEAL-1-NT. For each added cable proceed as per
section 11. The fiber splicing is outlined in section 7.

15.2 Reclose the closure with the sealing ring and the dome.

16

Slack storage tray kit (FOSC-D-BASKET)

16.1

If uncut loose buffer tubes are to be stored, the tube slack tray must be mounted. Detach

the splice trays from the tray mount by removing the retention bar and pulling out
splice trays.

16.2

Install slack tray by pushing the slack tray into the groove of the tray holder bracket.

16.3

For storing uncut loose buffer tubes, slide the fibers and slack loose tubes through the oval

port, being careful not to kink the tubes.

16.4

Store the slack inside the tray and hold in place with tie wraps.

16.5

Position assigned fibers/transportation tubes to be spliced in the splice trays.

16.6

Replace splice trays in tray mount bracket. (Splice trays will now be mounted above slack

tray.)