EntelliGuard® E Circuit Breaker

DEH-41526

24

©2012 General Electric All Rights Reserved

NETWORK INTERLOCK, SHUNT TRIP AND CLOSING COIL
DEVICE INSTALLATION

NOTICE

The mounting positions of the three devices can be
arranged in the locations as specified in Figure 7.3.


Figure 7.3. Device Location

Coil Position on Fascia

1&2 3

4

Network Interlock

closing coil

shunt

Shunt Trip & Closing Coil Installation (Fig. 7.4)
1. Tilt the device forward and engage the front hooks into

the top support plate.

2. Tilt the device backwards until the rear hooks engage

in the slots

3. Press down into position.

Figure 7.4. Closing Coil Installation

Connect the wire plugs (Fig. 7.5) according to the wiring
schematic in Section 3.


Figure 7.5. Wiring

Closing Coil Removal
1. Disconnect the device and pull it forward until the rear

hooks disengage.

2. Lift to release the front hooks.

NETWORK INTERLOCK INSTALLATION
When the network interlock is used with the EntelliGuard E,

it will use the 1 and 2 positions of the coils as shown in Fig.

7.3. The mounting procedure is same as the shunt trip and

closing coil.

BELL ALARM SWITCH INSTALLATION

1. Remove the trip unit from the PMU base.
2. Assemble the bell alarm assembly using four screws.
3. Reassemble the trip unit back onto the PMU base
4. Install the connector from the bell alarm in the specified

location of the SD.

SHUTTER PROP OPEN FEATURE
This feature allows the main primary contacts to be
inspected.

DANGER

ELECTROCUTION
Ensure the primary contacts on the swictchgear are de-
engergized prior to propping open the shutter.
Failure to comply with these instructions will result in
death or serious injury.

1. Remove the circuit breaker from its cassette.

2. Rotate the shutter operating lever to open the shutter

(Fig. 7.5).

3. Release the shutter operating lever to close the

shutters.


Figure 7.5. Shutter Operating Lever Location

A Shutter Operating Lever

CARRIAGE POSITION SWITCH INSTALLATION
One configuration is available:
Mounted on the left-hand side of the cassette for all frames.
No fasteners are required. To insert, feed the wires through
the large opening on the side of the cassette. Seat the
carriage position switch in the front side of the hole first.