GE Industrial Solutions Power-Vac ML-20 Mechanism User Manual

Page 12

Advertising
background image

12

8.4—Close Coil Plunger Gap

The close coil plunger gap is shown in Figure 8. With the

closing spring discharged, operate the plunger to make certain

that the plunger moves freely over its full stroke in the coil. To
check the closing coil plunger gap the breaker should be open

and the closing spring charged and gagged. Depress the close

plunger button until resistance is felt. The gap between the

plunger button and the coil housing should be as follows:

Figure 8 Close coil plunger gap



8.5—Trip Coil Plunger Gap

The trip coil plunger gap is shown in Figure 9. With the

breaker in the open position and the closing spring in the

charged position, make certain that the trip linkage and trip
shaft move freely over the full plunger travel. To check the trip

coil plunger gap adjustment, the breaker is to be closed with

the closing spring discharged. Dimension T between the

plunger button and the coil housing should be between 0.20

and 0.25 inch. This dimension is obtained when the trip
plunger button is depressed until resistance is felt. If the

breaker is equipped with an optional second trip coil, use

same procedure.

Figure 9 Trip coil plunger gap

8.6—Control Switch Adjustment

The breaker is to be in the open position with the opening and

closing springs discharged. This results in the control switch

plungers being in the depressed position. The switches to be

checked are shown in Figure 10. On the LCS and stacked
switches (SM/LS & CHG), the plunger rod is to be recessed

within the rear of the switch body and this recess is to be 0 to

1/32 inch. This is a visual check. No adjustment is required on

the CL/MS or the IL/MS.