5—close coil plunger, 6—close spring discharge interlock, Figure 13 spring discharge interlock – GE Industrial Solutions Power-Vac ML-20 Mechanism User Manual

Page 24: 7—negative interlock

Advertising
background image

24

Reference DIMENSIONAL CHECKS for breaker position and

spring status.

16.5—Close Coil Plunger

To adjust the close coil plunger gap, Figure 8, lift locktab away

from adjusting nut. Turn adjusting nut until close latch actuator

makes contact with close latch while maintaining the correct

plunger dimension. Bend locktab to secure adjusting nut.


Reference dimensional checks for required dimension and

breaker position and spring status.

16.6—Close Spring Discharge Interlock

THIS INTERLOCK IS FACTORY SET AND SHOULD NOT BE
ROUTINELY ADJUSTED IN THE FIELD. The adjustment for

this interlock is as follows. (See Figure 13).

CAUTION: THIS IS A SAFETY FEATURE

NOT A ROUTINE MAINTENANCE ITEM

Figure 13 Spring Discharge Interlock





The breaker should be open with the closing spring charged.

1. Back off 1/4 inch linkage adjusting screw.


2. While holding roller at 0.995 inch dimension, advance

adjusting screw to just touch interlock lever.

3. Check that spring discharges with roller at 0.561 inch

minimum dimension.


4. Close latch must reset as indicated.

16.7—Negative Interlock

THIS INTERLOCK IS FACTORY-SET AND SHOULD NOT BE

ROUTINELY ADJUSTED IN THE FIELD. The negative interlock
is adjusted with the breaker closed and the closing spring

discharged. (See Figure 23).

1. Hold roller at 0.670 inch from mechanism side plate.

Adjust linkage so the striker just makes contact with

properly adjusted trip linkage.

2. Lock in place with 1/4 inch hardware and rivet.

3. Check that breaker trips with roller at 0.531 inch minimum

dimension.


4. Check that linkage moves freely.