GE Industrial Solutions LP 33 Series 50 & 60 kVA Operating Manual User Manual

Page 52

Advertising
background image

Modifications reserved

Page 52/57

OPM_LPS_3UO_50K_60K_0US_V010.doc

Operating Manual LP 33 Series 50 & 60 kVA

7.2.8 Restore to normal operation after “EPO – Emergency Power Off”

NOTE !

Make sure the all units of the parallel system to be status of the activation of EPO, i. e.
Q1
closed, Q2 open and the battery breakers are in ON state.



View of the panel after pressing the button “EPO”:

x

All Contactors are open.

x

Booster, inverter and Static-Switch shutdown.

LP 33 60kVA P1

APPLICAT. SUPPLY OFF

= 0%




1. Reset

the

buttonEPO”.

Press Alarm, to reset alarm and buzzer.

01.06.2007 12:15:45
NR=255 Status=A588

4563:

EMERGENCY OFF

ACTIVATED

2.

Reset all UPS by entering the screen:

MENU/COMMAND MENU/INVERTER OFF

The load is supplied by the mains through the automatic
bypass
.

COMMAND MENU

INVERTER ON *
INVERTER OFF

The booster starts automatically.

The LCD screen must display on all Units the status:

APPLICATION ON BYPASS

LP 33 60kVA P1
APPLICATION ON BYPASS

= xx%

3.

Switch ON the inverter on first unit by entering the screen:

MENU/COMMAND MENU/INVERTER ON

In case of sufficient output power, the output will transfer to
Inverter

COMMAND MENU

INVERTER ON *
INVERTER OFF

4. Switch ON the inverter on the other units by entering the

screen: MENU/COMMAND MENU/INVERTER ON

(Do not start the next inverter until the sequence of the previous
one ends – about 10 seconds).

MENU COMANDI

INVERTER ON *
INVERTER OFF

LP 33 60kVA P1

APPLICATION ON UPS

= xx%

As soon as the output power of the inverters is sufficient to
supply the load, the output of the units with running inverter
will transfer to inverter.

The LCD screen must display on all Units the status:

APPLICATION ON UPS

END OF PROCEDURE

Advertising