7 OPERATION



START UP AND COMMISSIONING

A GE GLOBAL SERVICES FIELD ENGINEER must perform start-up and
commissioning of the UPS. Please Contact GE. Global Services at least
two weeks prior to schedule start-up and commissioning at 1-800-637-
1738, or by E-mail at

[email protected]

.





This symbol refers to the operations of a Parallel System.





NOTE !

Verify for correct input/output cabling before connecting Utility to the
UPS.
Open only the front door, do not remove any panels.

Check after every step for correct reaction of the UPS (LED’s on the
panel), and correct voltage and current measurements, before you
proceed to the next step.




Find on the following pages the descriptions of the various procedures of start-up and

shutdown for single and parallel UPS’s, divided into the following principal chapters:


7.1

PROCEDURES FOR SINGLE LP33 Series 80 & 100



7.2 PROCEDURES

FOR

LP33 Series 80 & 100 PARALLEL SYSTEM