6. In order to discharge the DC link capacitors, insert the inverter by pressing Inverter ON ( I ) key

on all UPS units.

`

Home\Meter

INVERTER

f :

60.0

Hz

L1 :

7

V

L2 :

7

V

L3 :

7

V

T :

OK

SYNCHRONIZED

Remark:
Command INVERTER ON will be enabled only when the inverter

voltage of each phase decreases below 7 Vac (about 30 seconds).

`

Home\ Meter

BOOSTER

f :

60.0

Hz

L1 :

120

V

L2 :

120

V

L3 :

120

V

Vp :

5

V

Vn :

5

V

Before proceeding to step 7, check on the display panel that the DC

link voltage (both polarities) Vp and Vn has reached the max.

voltage of 5 Vdc (about 30 seconds).

The acoustical alarm is activated, press “MUTE” key (from Home
screen) to reset it.

7. Disconnect the inverter, on all UPS units, by pressing Inverter OFF ( O ) key and hold until the

LED Inverter (7) turns OFF.

The load is now powered directly by utility through all
MANUAL BYPASS Q2
.
The synoptic diagram, on all UPS units, must display the

statusLOAD SUPPLIED BY MANUAL BYPASS Q2.

END OF PROCEDURE



WARNING !

If the above procedure is not completely performed, it could cause
serious damages to the UPS.
In case the procedure described on step “6 - Discharge DC link capacitors”
cannot
be completely performed, the DC capacitors could be charged with dangerous
voltage for a minimum of 5 minutes.
Wait until capacitors are completely discharged before starting the UPS again.
The UPS cabinet contains parts electrically live
.
Apart from the front door, do not open any other part of the UPS.


NOTE !

With separate utility inputs, it’s possible to disconnect utility rectifier.