CAUTION !

Panel “D” should never be removed or replaced with power applied to the UPS.
This panel is in close proximity to 480V live buss bars.
Always disconnect the rectifier, bypass, load and battery sources from the UPS before
removing or replacing this panel.

If not serious injury or death could occur!

How to access the compression lugs for the cable connections.

Top entry cables

S

G

T500

0_10

0-15

0_UP

S

conn

ec

ti

on

_01U

S

E

A

B

D

C

Bottom entry cables

2

4

3

1

4

3

2

1

Q1

Q2

!

Please remove the plate
before drilling any wholes.

Please remove the plate
before drilling any wholes.

!

Fig. 3.8.1-1 Access to the input / output connections

To access input, output and Battery Connections proceed as follows:

• Unscrew bolts “B” to open the electronics “A”.
• Remove protection panel “C”.
• Remove protection panel “D”.
• Remove UPS side panel “E”.

Position of the compression lugs, depending whether cable input is from top or bottom of the UPS.

SGT50

00_100

-150_Lu

gs conn

ection b

ottom_0

1

Fig. 3.8.1-2 Position for bottom input

SitePro

A_100-

150_Lu

gs conn

ection t

op_01

Fig. 3.8.1-3 Position for input from top

Modifications reserved

Page 22/37

OPM_SGS_ISG_M10_M15_0US_V040.doc

Installation Guide SG Series 100 –120 – 150 kVA