S47183De rev.02 2011-03-14

Fig. 55-4 Unscrew all the plugs from control boards

Fig. 55-5 Pull out the plugs of the control boards. Pull out
selected control board. Insert new control board

 Listen that both, the isolation plate at the side of equipment

and the isolation plate at the side of soldering, were inserted!


Fig. 55-6 Plug in all control plugs and tighten it by the
screws.

Fig. 55-7 Pay attention, that no cables will be pinched
between box and front cover during closing!

Fig. 55-8 Carefully replace the control box front cover and

attach the with the four screws

 Put on plugs X2…X6, fix the screws of the plugs and switch

on control voltage.


Checking the breaker:

Open and Close the breaker 3 times while it is

disconnected from the system (in the “Test-position“ of
the draw out version/the installation). The breaker must

open and close without a time delay over 400 ms.


If the test succeeds, reconnect the breaker to the main
circuit.

6.2.2 Layout of control PCB inside control box