3.3.4 Connecting internal batteries (for 8/10 kVA models only)


The internal battery packs are shipped separately from the UPS cabinet. They have to be mounted
inside the unit after the UPS installation. Please proceed with the following steps:


1. Unpack the 2 battery packs

from their carton box.


2. Place the battery packs side by

side in the battery
compartment (2, fig. 3.3.4.a).


3. Fix the 2 battery brackets with

the screw set to hold battery
packs into the cabinet
(3, fig.3.3.4.a).


4. Connect the UPS DC

connectors of each battery
pack (4, fig.3.3.4.a).


5. Fix the battery grille in front of

the battery compartment with
3 screws (5, fig.3.3.4.b).

6. Mount the front panels by

pushing the plastic part into
the appropriate position
(6, fig. 3.3.4.c).


7. Proceed with the UPS

preparation.

fig. 3.3.4.a

fig. 3.3.4.b

fig. 3.3.4.c

8/10 kVA

8/10 kVA

8/10 kVA

modifications reserved

12

User manual GT Series 5/6/8/10 kVA UPS 1.0 (US)

Advertising