Installation Procedures

The ground mount assembly enables 180° positioning for selected azimuth viewing.
Azimuth range coverage is ±90° divided into three 120° continuous ranges with 30°
overlap. Elevation adjustment is continuous from 0 to 90°.

Position and mount 204737 azimuth tiller arm weldment to ground mount assembly as
shown using 0.75 x 1.75 in. A-325 bolts and nuts. Tighten hardware per A-325 tension-
ing procedure. NOTE: Mounting position of azimuth tiller arm weldment is dependent
upon predetermined azimuth range requirements as shown.

Apply supplied stick lubricant to set screw threads. Loosely install 0.50 x 1.0 in. set
screws in azimuth and 0.50 x 1.50 in. set screws in elevation strut supports.

Position and mount 204754 elevation support angle assembly to ground mount as
shown using 0.50 x 1.75 in. A-325 bolts, flat washers and nuts. Tighten hardware per A-
325 tensioning procedure.

Loosely install supplied 0.75 x 2.00 in. A-325 bolts, flat washers and nuts in elevation
support angle assembly. This hardware along with the upper elevation strut hardware
will be attached to the antenna and tightened to the A-325 tensioning procedure at the
time of antenna installation.

Support Plate

1/2 x 1” Bolt and

Flat Washer

3/4” Threaded

Rod

3/4” Flat

Washer

Pivot Block

3/4 x 1-3/4”

Bolt and Nut

EL SPT Angle

Assembly

AZ Tiller Arm

Weldment

3/4 x 2” Bolt and Flat Washer

(2 Washers per Bolt, one each

on Reflector and Mount Side)

Figure 3-8b: Ground Mount Assembly Tiller Arm Hardware