background image

Appendix G-2 Turbine Installation QA Checklist

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of this

document.


DOC012R02 AOC 15/50 User Manual Nov 2001

152

Turbine Number

Customer

Inspection of Shipped Components

Check

Inspect blades for damage

Inspect turbine assembly for damage

Check sight glass to verify transmission oil level

Inspect electrical components and cables for damage

Inspect tower components for damage

Q.A. Date

Tower Assembly and Tower Erection

Check

Braces installed with bolt heads inboard, locking nuts outboard

1" flange bolts torqued to 250 ft/lbs

5/8" brace nuts torqued to 150 ft/lbs

Pal nuts installed on bolts indicating fully torqued

Confirm anchor bolts undamaged

Tighten anchor bolts snug tight, with locking washers installed

Verify tower base is level

Tower is grounded on each leg

Tower base flange grouted with drain

Assy by Q.A. Date

Blade Mounting

Check

Clean blade root inserts with Loctite cleaner

Ensure correct blade pitch angle

Remove all paint and rust from hub blade bolt counterbores

Blade washers aligned and seated properly and in counter bore

Apply primer and Loctite 271 to all blade bolts

Torque blade bolts to 180 ft/lbs

Assy by

Q.A.

Date