4.0 Planning and Installation Checklist

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer

on page v of this document.


DOC012R02 AOC 15/50 User Manual Nov 2001

25

Line protection required

Cogeneration standards for small power producers

Interconnection hardware and wiring standards

System operation requirements:
§ Voltage regulation
§ Power factor
§ Protective devices
§ Utility/wind turbine interface responsibilities

To interface with the utility network correctly all power factor correction capacitors or
unique loads connected to the utility system need to be identified by the customer.
Furthermore, the Required Customer Power Grid Information sheet should be completed to
assist AOC in designing the most suitable interface. See Appendix K.

4.3 Permits and Approvals


Local authorities often require a wind turbine operator to obtain permits or approvals, some of
which have been identified below. It is important to determine which of these apply to a site
and whether any independent inspections are required.

Issuing Authority:

Municipality or local council

Country

State or Province

Federal (FAA, FCC, etc.)

Commission (energy, conservation, historic, etc.)

Utility


Type:

Construction

Foundation engineering

Electrical works

Interconnection

Zoning

Communication interference

Aviation interference

Environmental impact

4.4 Plans and Drawings