6.0 Tower and Wind Turbine Generator Installation

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer

on page v of this document.


DOC012R02 AOC 15/50 User Manual Nov 2001

48

technician standing on a platform (see Figure 6-14). The same procedures for attaching and
aligning the third blade should be used as were described in Section 6.4.




APPROXIMATE C. G. LINE

Figure 6-13 Wind turbine generator lift

When all blades and tip brakes have been mounted correctly, the parking brake should be
engaged and a tagline attached to the two downward pointing blades, around the tip brake hinge
point. The twist cable attached to the base of the wind turbine generator should be looped and
tied so that it is lifted with the turbine.

All necessary tools (see Appendix I) and hardware (mounting bolts, nuts and washers) should be
taken to the top of the tower. 1" non-locking nuts are useful as quick fasteners to secure the
tower top casting to the tower temporarily. These items may be raised together with the wind