AOC 15/50 Commissioning Test QA Checklist

T u r b i n e N u m b e r

C u s t o m e r

Control Box Check

Q A C h e c k

Date

Inspect cabling to control boxes

Emergency Stop

Q A C h e c k

Date

Confirm function of Emergency Stop switch (MCR disabled)

Parking Brake release

Q A C h e c k

Date

Confirm electrical release of Parking Brake

(Rotor should turn if wind present)

NOTE: Parking brake release should produce an audible click

Anemometer Signal Check

Q A C h e c k

Date

W ith computer interface, check for signal from both units

( 0 - 5 V = 0 - 1 0 0 m p h )

Conduct Rotor Jog

Confirm Directional Rotation
Confirm RPM (50Hz 1495-1530 and 60Hz 1790-1830)

Q A C h e c k

Date

Confirm tip brakes do not deploy

Dynamic Brake Test

Check connection of 1M and 4M wires (control wires)
Observe sufficient drop in RPM

Q A C h e c k

Date

(33-50% drop without tip brakes or parking brake deployed)

C A U T I O N : D O N O T R U N D Y N A M I C B R A K E F O R L O N G E R T H A N T E N ( 1 0 ) S E C O N D S .
A L L O W R E S I S T O R S T O C O O L T O R O O M T E M P E R A T U R E B E F O R E R E P E A T I N G T E S T

Placing Turbine On Line

Q A C h e c k

Date

Observe turbine coming on line

Manual Shutdown

Confirm turbine coming off line

Q A C h e c k

Date

Turn turbine power switch to "OFF"

L o w W i n d S h u t d o w n

Q A C h e c k

Date

Observe low-wind shutdown.

(If conditions do not permit, simulate electrically)