4.0 Planning and Installation Checklist

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer

on page v of this document.


DOC012R02 AOC 15/50 User Manual Nov 2001

29

Day 1:

Plan and prepare erection

Assemble tower

Test generator and use it as a motor to test drive train

Clean blades and install tip brake cable

Prepare tip brake studs and cavity

Prepare blade bolt inserts

Attach twist cable

Install two of three blades if time permits (fork lift, boom truck, etc.)


Day 2:

Lift and install tower on foundation (crane)

Install blades on hub

Install tip brakes on blade ends

Lift and mount machine onto the tower

Torque tower top fasteners

Torque all tower bolts and add pal nuts


Day 3:

Install and wire anemometers

Wire twist cable junction box and disconnect (if applicable) at tower base

Grout tower legs

Mount warning signs as required

Troubleshoot and commission


Day 4:

Complete any further installation details

Carry out final QA check

Monitor performance (wind permitting)