Alto-Shaam 12.18ESG User Manual

Page 21

Advertising
background image

G A S C O M B I T H E R M

I N S T A L L A T I O N M A N U A L

#MN-28898

PG

. 19

G A S S U P P LY & I N S TA L L AT I O N R E Q U I R E M E N T S

®

C O M B I T HE R M

LEAK TESTING

If a pressure leak test above 1/2 psi is to be

performed on the building supply gas piping, the

shut-off gas valve and oven inlet gas supply line

must be disconnected from the building supply

piping before conducting the pressure test. Failure

to do so may result in damage to the manual gas

valve, gas components in the oven, or both.
If any gas leak tests are to be conducted at pressures

equal to or below 1/2 psi, the manual gas shut-off

valve upstream of the oven must be turned off

before conducting the tests.
Leak testing of the internal oven piping system was

conducted before shipping the oven from the

factory. If additional testing is needed, it should

only be conducted at normal gas supply pressures.

If the testing is performed using combustible gas in

the piping, the leak checking should be done with a

soap solution (bubble checking).

The use of an electronic combustible gas leak detector

is helpful, however, this type of detector can

be oversensitive. Electronic detectors may indicate

false leaks from other sources which would not be

detected when checking with a liquid solution to

verify a no-hazard gas connection.

When starting the oven after initial installation, the

gas lines must be free of air. It may take up to 30

minutes to eliminate all air from the lines. If, after

this time there is no pilot, call for factory assistance.

GAS EXHAUST

The oven is not designed for direct connection to

a chimney vent system or for direct connection

to a horizontal exhaust system.
The oven must be installed under a ventilation

hood listed to ANSI/UL 705 (latest edition),

and the installation must be completed in

accordance with the ANSI/NFPA 96-1987,

Standard for Ventilation Control and Fire

Protection of Commercial Cooking Operations.
Oven operators should be instructed with regard

to the hazards of placing any material on top of

the oven that would obstruct the flow of flue

products out the opening of

the flue diverter. Operators

should also be instructed

with regard to the hazards of

hot flue gases and that any

material or items placed on

top of, or in front of the flue

defector could be damaged or

cause a fire hazard.

D A N G E R

NEVER USE AN OPEN

FLAME TO LEAK TEST.

D A N G E R

BEFORE STARTING THE
APPLIANCE, MAKE CERTAIN
YOU DO NOT DETECT THE
ODOR OF GAS.

IF THE ODOR OF GAS IS DETECTED:
• DO NOT attempt to light any appliance.
• DO NOT touch any electrical switches.
• Extinguish any open flame.
• Use a telephone OUTSIDE THE

PROPERTY & IMMEDIATELY
contact your gas supplier.

• If unable to contact your gas supplier,

contact the fire department.

Advertising
This manual is related to the following products: