21. Assemble the 5 or 7 special bolts (1) and screw in

finger tight. Remove and replace the two alignment
studs with bolts after the other bolts are in place.
Alternately and progressively tighten the bolts to pull
the end cover and other components into place with
a final torque of 22-26 ft. lbs. 45-55 ft. lbs.(61-75 N
m) for the seven 3/8-24 threaded bolts.

NOTE: The special bolts required for use with the relief or

shuttle valve (24) end cover assembly (2) are longer
than the bolts required with standard and cover
assembly. Refer to the individual service parts lists
or parts list charts for correct service part number if
replacement is required.

22. Torque the two shuttle valve plug assemblies (21) in

end cover assembly to 9-12 ft. lbs. (12-16 N m) if
cover is so equipped.

Torque the two relief valve plug assemblies (21) in
end cover assembly to 45-55 ft. lbs.(61-75 N m) if
cover is so equipped.

One Piece Stator Construction

A disassembled rotor (8A) stator (8B) and vanes (8C) that
cannot be readily assembled by hand can be assembled
by the following procedures.

1. Place stator (8B) onto wear plate (9) with seal ring

(4) side down, after following Torqlink™ assembly
procedures 1 through 13. Be sure the seal ring is in
place.

2. If assembly alignment studs are not being utilized,

align stator bolt holes with wear plate and housing
bolt holes and turn two bolts (1) finger tight into bolt
holes approximately 180 degrees apart to retain sta-
tor and wear plate stationary.