Hydrometers Operation and Maintenance Manual

Operational Testing

INSTALLATION

Before the hydrometer is placed into service, you should perform the following tests to verify that

it is operating properly:

A. To test water flow and manual operation:

• Set 3-Way Selector to the “Open position”.

• Turn on the water flow to the hydrometer.

• Visually verify that water is flowing downstream from the hydrometer in appropriate

quantities.

• Verify that the leak detector, pointers and the totalizer are functioning properly.

• Check all hoses, connections, pilot valves, etc. for leakage and repair as necessary.

• Set 3-Way Selector to the “Close position”.

• Verify that the water flow downstream has stopped.

B. To test automatic and remote operation:

• Set 3-Way Selector to the “Auto” position.

• Turn on the water flow to hydrometer.

• Verify that the hydrometer output is correctly received by the controller or control center.

• Use the controller or control center to close the hydrometer. Verify that the water flow

downstream has stopped.

• Use the controller software to test operation of the hydrometer under various applications

and conditions such as pressure reducing, pressure sustaining and flow regulation.

• Your hydrometer is now ready for routine use.