Installation

CAUTION:

If installing an optional EBM, make provision for installing the EBM directly below the UPS with

no U space between the UPS and EBM.

4

Position the left and right rails as illustrated (see Figure 10).

NOTE:

Observe the labels on the rails for right front (labeled RIGHT FRONT) and left front (labeled LEFT

FRONT).

5

Attach the left and right rails to the rack:

Engage the back end of the rail until it fully seats on the vertical rack flange and the hook latch

locks in place (see Figure 10).

Pull the rail just past the front of the rack.

Push the front end of the rail until it fully seats on the vertical rack flange and the hook latch locks

in place.

Figure 10. Installing the Rails