Back brace, P80/pp25 operator’s manual – Ditch Witch P80 User Manual

Page 46

Advertising
background image

P80/PP25 Operator’s Manual

Push Rods - 45

Setup

CMW

Back Brace

1.

Dig starting trench 18” (460 mm) wide and 72-99” (1830-2500 mm) long.

2.

Level and compact trench floors.

3.

Dig target trench deep enough to meet bore path and long enough to remove rod.

4.

Slide a rod through cylinder and install pilot head.

5.

Fasten chain and lift rod pusher in level position. Lower
unit into trench.

6.

Attach hydraulic control hoses to power unit hydraulic
manifold. Connect other hoses from hydraulic control
valve block to rod pusher.

7.

Align unit with intended bore path.

8.

Place a level on push rod at rear of unit. Adjust angle to
match grade of bore.

Advertising