Altera PowerPlay Early Power Estimator User Manual

Page 42

Advertising
background image

3–24

Altera

Corporation

PowerPlay Early Power Estimator For Stratix II, Stratix II GX & HardCopy II

January 2007

PowerPlay Early Power Estimator Inputs

The PowerPlay Early Power Estimator spreadsheet also verifies that the
V

CCIO

levels match the I/O standards for each I/O bank. If there is a

discrepancy, it is displayed in the Bank Voltage Check column, as shown
in

Figure 3–14

.

Figure 3–14. PowerPlay Early Power Estimator Spreadsheet Checks for V

CCIO

Inconsistencies

1

Importing the Quartus II estimation file automatically populates
the V

CCIO

voltages. However, certain designs may have

discrepancies. This occurs most often if I/O standards that are
listed as different voltages in the PowerPlay Early Power
Estimator spreadsheet can actually be in the same I/O bank on
the device.

f

For more information on I/O standard guidelines, see the Selectable I/O
Standards in Stratix II Devices
chapter in volume 2 of the Stratix II Device
Handbook
.

If there are discrepancies between the V

CCIO

voltages in banks, the

PowerPlay Early Power Estimator spreadsheet displays the following
message:

Bank and I/O voltage selection inconsistent with I/O Bank Voltage. See
the Bank Voltage column.

Ensure that the correct V

CCIO

is selected for the bank.

Advertising