C. Vertical Penetration Framing

Installing the Ceiling Firestop

• Frame an opening 10 inches by 10

inches whenever the vent system
penetrates a ceiling/fl oor (see Figure
6.4).

• Frame the area with the same sized

lumber as used in ceiling/fl oor joist.

• When installing a top vent vertical ter-

mination appliance the hole should be
directly above the appliance, unless the
fl ue is offset.

• Do not pack insulation around the vent.

Insulation must be kept away from the
pipe.

Figure 6.4

ATTIC ABOVE

10 IN. (254 MM)

HOLE SHOULD MEASURE

10 IN. X 10 IN.

(254 MM X 254 MM)

INSIDE TO INSIDE

10 IN.

(254 MM)

WARNING

Fire Hazard

Keep loose materials or blown
insulation from touching the
vent pipe.

Installing Attic Shield

Note: An additional ceiling fi restop is not
required if attic shield is used.

• Frame opening for attic shield.

• Attic shield may be installed above or

below ceiling (see Figure 6.5).

• Secure with three fasteners on each

side.

• Fold tabs at top of attic shield in toward

vent pipe. Tabs must keep vent pipe
centered within shield.

• Field construct additional shield height if

insulation is deeper than height of attic
shield.

Figure 6.5 Installing the Attic Shield

National building codes recommend us-
ing attic shield to keep loose materials/
blown insulation from contacting vent.

Hearth & Home Technologies requires
the use of an attic shield.

3 FASTENERS

PER SIDE

BEND TABS IN

AROUND PIPE

ATTIC SHIELD INSTALLED

BELOW CEILING

ATTIC SHIELD INSTALLED

ABOVE CEILING