Figure 11 - Termination Cap Locations

DIMENSION DESCRIPTIONS

A

Clearance above the ground, a veranda, porch, deck or bal-

cony - 12 inches (30 cm) minimum. *

B

Clearance to window or door that may be opened – 10,000

BTUs or less, 6 inches (15 cm) minimum; 10,000-50,000 BTUs,

9 inches (23 cm) minimum; over 50,000 BTUs, 12 inches (30

cm) minimum. *

C

Clearance to permanently closed window – 12 inches (30

cm) minimum - recommended to prevent condensation on

window.

D

Vertical clearance to ventilated soffit located above the termi-

nation within a horizontal distance of 2 feet (60 cm) from the

centerline of the termination – 18 inches (46 cm) minimum. **

E

Vertical clearance to unventilated soffit - 12 inches (30 cm)

minimum. **

F

Clearance to outside corner - 6 inches (15 cm) minimum.

G

Clearance to inside corner - 6 inches (15 cm) minimum.

H

Not to be installed above a meter/regulator assembly within 3

feet (90 cm) horizontally* from the center line of the regulator

I

Clearance to service regulator vent outlet - 6 feet (1.8m)

minimum. *

J

Clearance to non-mechanical air supply inlet into building or

the combustion air inlet to any other appliance - 12 inches (30

cm) minimum. *

K

Clearance to mechanical air supply inlet - 6 feet (1.8 m)

minimum. *

L

Clearance above a paved sidewalk or paved driveway lo-

cated on public property - 7 feet (2.1 m) minimum.
A vent may not terminate directly above a sidewalk or paved

driveway which is located between two single family dwell-

ings and serves both dwellings.

M

Clearance under veranda, porch, deck or balcony - 12 inches

(30 cm) minimum. * Recommended 30 inches (76 cm) for vinyl

or plastic.
Only permitted if veranda, porch, deck or balcony is fully

open on a minimum of 2 sides beneath the floor. *

N

Vertical clearance between two horizontal termination caps

– 12 inches (30 cm) minimum.

O

Horizontal clearance between two horizontal termination caps

– 12 inches (30 cm) minimum.

*

As specified in CGA B149 Installation Codes

Note: Local codes or regulations may require different clear-

ances.

**

Clearance required to vinyl soffit material – 30 inches (76 cm)

minimum. With a vinyl soffit shield – 18 inches (46 cm) mini-

mum.

WARNING!

In the U.S.: Vent system termination is NOT permitted in

screened porches. You must follow side wall, overhang and

ground clearances as stated in the instructions.
In Canada: Vent system termination is NOT permitted in

screened porches. Vent system termination is permitted in

porch areas with two or more sides open. You must follow all

side wall, overhang and ground clearances as stated in the

instructions.
Hearth & Home Technologies assumes no responsibility for

the improper performance of the appliance when the venting

system does not meet these requirements.

Figure 12 - Cap Clearances

Advertising