CONTROL BOX MOUNTING

Actuator Control Box Mounting

1)

Mark the third sidewall
ring from the ground to
indicate the cable path if
dump chutes and cable are
already installed.

2)

Make sure that all dump
chutes and chains are
EVENLY adjusted so that
when one chute is level
the others are level as
well.

3)

Keep in mind that wire
will be used to
interconnect the Actuator
Control Box with the
Autoflow Control Box;
and, that a 110V power
supply will need to run
from the entrance panel to
the Actuator Control Box
to power the 24V DC
battery charger.

4)

Use the pattern in Figure
3 to drill holes for the
Actuator Control Box.

5)

If the horizontal seam
bolts are within 1”
horizontally of the hole
pattern shown, existing
holes may be used to
attach the actuator.

6)

Use four 5/16” x 1.1/4”
bin bolts and washers
with bolt heads to the

inside of the bin.

7)

Do not attach the dump chute cable to the actuator at
this time. The cable should not be installed until after
the actuator unit is completely wired and tested.