penetrating the Roof

Run pipe to roofline. Since chimney system must be

vented to the out-of-doors, you

must use an approved

MHSC termination.
If a chase is used, refer to the installation manual pro-

vided with the termination cap.

locate chimney centerpoint on Roof

Use same procedure detailed in locating center point of

the flue system.
Drive a nail up through roof at the center point. This will

determine center point on outside of the roof.

cut and Frame Roof hole

Size of roof hole varies with the type of chimney ter-

mination installed. Refer to installation instructions

provided with MHSC chimney termination to find correct

size of roof hole.
There must be a 2” (51 mm) air space between out-

ermost portion of chimney sections and any adjacent

combustible surfaces. (Combustible surfaces include

burnable materials such as: ceiling members, joists,

flooring, combustible insulation and roof structures.)
WARNiNg: Do not pack required air spaces with

insulation or other materials.
Mark an outline of the roof hole around the center of the

point nail.

NoTE: Hole dimensions given in the chim-

ney top installation instructions are

horizontal dimen-

sions; therefore, the hole size must be marked on the

roof accordingly.
Cover the opening of the installed chimney so debris

cannot get into the system.
Cut and frame the hole. It is good practice to use fram-

ing lumber that is the same size as the rafters. Install

the frame securely because the chimney top and flash-

ing anchored to the frame must be able to withstand

heavy winds.

install Remainder of chimney Sections

Since you have already preplanned the height of your

termination according to the Ten Foot Rule, continue to

install pipe to the predetermined height.
Check the chimney top installation instructions for

details on how high above the roof top the chimney sec-

tions (all pipes) should extend.

install Top housing or Termination

Follow the installation instructions provided with the

chimney termination you have selected.

FP1199

EPA36

AIR SPACES

circulating models

3/20/02 djt

Air Space clearances

Combustible framing material MUST NOT

penetrate AIR SPACE (shaded areas)

Standoff

2”

(51mm)

Firestop

1” (25mm)

Space to Back

1” (25mm)

Air Space

to Sides

Wall

Shield

0” Clearance

to Floor

Hearth Extension

FP1199

Fig. 20 Minimum clearances to combustibles.

1” (25mm) Air

Space to Sides

No mate-

rial may

cover cast

face

installing chimney in a chase

Refer to Figure 2, Page 5 for an illustration of a typical

chase installation.
cAUTioN: Treatment of firestop spacers and construc-

tion of chase may vary with type of building. These

instructions are not a substitute for local building codes.

You

must check your local building codes to determine

specific requirements for your city or state.

NoTE:

Other building materials may be required in addition to

MHSC Firestop Spacers.

Finishing

cAUTioN: All joints between the finished wall and

the fireplace surround (steel front) must be sealed with

noncombustible material to prevent cold air leakage into

the room. (Fig. 20)
NoTE: No material may cover black cast face.

Advertising