Castile Pellet Insert

Install Sides

First

Install Front Last

Bend top and bottom tabs toward inside

NOTE: Manually

pre-shape sides before

installing

Turn right side up and attach top cast rin g

Zero Clearance Panel Extension

Alignment

Hole

Cast Trim

Footer

Panel Leg

Base Plate Only Installation

Parts Needed: (1) cast ring (2) base zero clearance panel
extensions. Discard balance of parts.

Tools Needed: Phillips head screwdriver

1. Attach base zero clearance panel extensions to cast

ring.

2. Place assembly under appliance.

1. Remove contents from box and lay on protective surface

to avoid scratching the paint.

2. Lay zero clearance front and sides face down. Bend the

tab down toward the inside.

3. The side pieces are shipped fl at. It is much easier to

manually fl ex the sides into a bowed position before

installing.

4. Lay 1 cast ring face up, which will become the bottom ring

when installed. Attach the 2 sides FIRST and then the

front piece. Figure 20.1.

5. Now turn the cast ring right side up and attach the top cast

ring . Figure 20.2.

6. Attach the zero clearance panel extensions. Figure

20.3

7. Attach cast footers. Figure 20.4.

8. Place the assembled zero clearance trim support under

the insert. Figure 20.5.

Zero Clearance
Panel Extension

Panel Leg

Cast Trim Footer

D. Zero Clearance Trim Support (Cont’d)

Figure 20.1

Figure 20.2

Figure 20.3

Figure 20.4

Figure 20.5